GRES-2 power plant - a thermal power station located in Jekybastuz, Kazakhstan. It was built in 1987. The installed capacity of the power plant is 1000 MW. It has the highest chimney in the world measuring 419.7 meters tall, which is 39.7 m higher than the Inco Superstack chimney.

The power plant is the starting point of the Jekybastuz-Kokczetaw power line, constructed for the world's highest 1150 kV transmission voltage. Technical data

The power plant was planned for 4000 MW using 8 identical units of 500 MWe each. Block 1 was launched in December 1990. Block 2 was launched in December 1993. Block 3 was started in 1990 but was not completed.